48

turbines to be installed and connected to the grid

168m

height of wind turbines

June 2018

Construction Commenced

111 118

homes to be powered
Wind Turbine Facts
FAQs

Transportation schedule

This week

WEEK
5
Monday
27 January
5 x Tower sections via [Atlantis Route]
4 x Blades via [Saldanha Route]

This week

WEEK
5
Tuesday
28 January
No scheduled transportation

This week

WEEK
5
Wednesday
29 January
No scheduled transportation

This week

WEEK
5
Thursday
30 January
4 x Tower sections via [Atlantis Route]
4 x Blades via [Saldanha Route]

This week

WEEK
5
Friday
31 January
No scheduled transportation

Next week

WEEK
6
Monday
3 February
3 x Tower Sections via [Atlantis Route]
4 x Blades via [Saldanha Route]

Next week

WEEK
6
Tuesday
21 January
No scheduled transportation

Next week

WEEK
6
Wednesday
5 February
No scheduled transportation

Next week

WEEK
6
Thursday
6 February
2 x Tower Sections via [Atlantis Route]
3 x Blades via [Saldanha Route]

Next week

WEEK
6
Friday
7 February
No scheduled transportation