48

turbines to be installed and connected to the grid

168m

height of wind turbines

June 2018

Construction Commenced

95 000

homes to be powered
Wind Turbine Facts
FAQs

Transportation schedule

This week

WEEK
32
Monday
5 August
5 x tower sections via [Atlantis Route]
1 x hub, 1 x nacelle, 3 blades via [Saldanha Route]

This week

WEEK
32
Tuesday
6 August
No scheduled transportation

This week

WEEK
32
Wednesday
7 August
5 x tower sections via [Atlantis Route]
1 x Nacelle, 1 x Hub, 3 x Blades via [Saldanha]

This week

WEEK
32
Thursday
8 August
No scheduled transportation

This week

WEEK
32
Friday
9 August
No scheduled transportation

Next week

WEEK
33
Monday
12 August
5 x Tower sections via [Atlantis Route]
1 x nacelle, 1 x hub, 3 blades via [Saldanha Route]

Next week

WEEK
33
Tuesday
13 August
No scheduled transportation

Next week

WEEK
33
Wednesday
14 August
No scheduled transportation

Next week

WEEK
33
Thursday
15 August
5 x Tower Sections via [Atlantis Route]
1 x Nacelle, 1 x Hub, 3 x Blades via [Saldanha Route]

Next week

WEEK
33
Friday
16 August
No scheduled transportation

48

turbines to be installed and connected to the grid

168m

height of wind turbines

June 2018

Construction Commenced

95 000

homes to be powered
Wind Turbine Facts